1 | Deployment of resources & manpower for carrying out the pending mechanical works ie; installation of pressure parts attachments & tension bar plates, lug plates and field welded lug in field welded wind box corner assy. At boiler unit#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/PENDING WORKS/PP ATTACHMENTS OF FIELD WELDED BOX CORNER ASSY./U#1/WO/6461 | 08.03.2022 | 25 DAYS | 1,775,000 | |
2 | Deployment of 8 nos skilled, 9 nos un skilled manpower,01 no. supervisor and 01 no. safety supervisor for civil works of APH CHP As per terms & conditions of enquiry no. BHE/PW/RGMT/MISC.CVL-03 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RGMT/CVL/MANPOWER-03/6004A | 14.09.2022 | 60 DAYS | 1,418,100 | |
3 | Deployment of 7 nos skilled manpower, and 1 nos supervisor for civil works of AHP CHP as per terms & conditions of our enquiry no.BHE/PW/RGMT/MISC.CVL-07/6029 A | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RGMT/CVL/MANPOWER-06/6067A | 09.10.2022 | 90 DAYS | 1,639,800 | |
4 | Deployment of 8nos skilled manpower, 10 nos unskilled manpower and 1 no supervisor for civil works of AHP CHP as per terms & conditions of our enquiry no.BHE/PW/RGMT/MISC. CVL-08/6106A | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RGMT/CVL/MANPOWER-304/6140A | 14.11.2022 | 75 DAYS | 1,685,250 | |
5 | Deployment of 5 nos skilled manpower , 10 nos unskilled manpower and 1 no supervisor for civil works of AHP CHP as per termss & conditions of our enquiry no.BHE/PW/RGMT/MISC. CVL-07/6064 B | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RGMT/CVL/MANPOWER-07/6075A | 15.10.2022 | 90 DAYS | 1,660,500 | |
6 | Completion of RE-Heater spary system piping works in all respect including H&S and excluding preheating, heat treatment & its NDT part of boiler u#3 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/RE-HEATER SPRAY SYSTEM PIPING WORKS/U1-BOILER/WO 6149 | 19.11.2022 | 60 DAYS | 1,900,000 | |
7 | Deployment of 5nos skilled manpower, 10nos unskilled manpower and 1nos supervision for civil works of AHP CHP as per terms & conditions of our enquiry No.BHE/PW/RGMT/MISC CVL-10/6250A | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RGMT/CVL/MANPOWER-10/6293A | 11.01.2023 | 15 DAYS | 271,200 | |
8 | Deployment of 7Nos skilled manpower, 10 nos unskilled manpower for civil works of AHP CHP as per terms & conditions of our enquiry no.BHE/PW/RGMT/MISC.CVL-11/62664 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RGMT/CVL/MANPOWER-11/6318A | 16.01.2023 | 14 DAYS | 274,540 | |
9 | Rectification/ Restoration works of boiler U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/PACKAGE-C MECHANICAL WORKS/FRH ROOF SEAL BAND SEEPAGE/RESTORATION/6148b | 20.02.2023 | 50 DAYS | 9,010,000 | Work Completion Certificate available |
10 | Deployment of resources for carrying out the pending works in all respect for LHS Wall blower piping system including supports at boiler U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/WALL BLOWER LHS & FRONT/U#1/WO/643913 | 27.02.2023 | 45 DAYS | 1,752,000 | |
11 | Deployment of resources for carrying out the pending works in all respect for RHS & REAR wall blower piping system including supports at boiler U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/WALLBLOWER PIPING RHS & REAR/ U#1/WO/6441 | 28.02.2023 | 45 DAYS | 1,800,000 | |
12 | Deployment of sepaeate agency for carrying out the pending mechanical works in all respect in rectification of damaged/bend tube and dislodge of flexible male and female connector assembly od super heater platen rear coil assembly at unit#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/Mechanical work/Sh. Platen coil assy./Restoration/WO/6446 | 01.03.2023 | 10 DAYS | 370,000 | |
13 | Deployment of separate agency for carrying out the pending mechanical works ie:normalisation of super heater spray water piping control after steam blowing activity like installation of block valves, control valves, NRV, flowmeter with root valves, drain & vent valves, thermowells & normalization of SH. spray inlet link piping with eco link & desuperheater and warm up line W-03 connection with S-3 spray water piping at boiler U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/SPRAY PIPING SYSTEM/NORMALISATIONWORK/U#1/WO/6462 | 09.03.2023 | 25 DAYS | 1,875,000 | |
14 | Deployment of resources for carrying out the pending mechanical works i.e., removal of the foregin materail noticed in boroscopic inspection of headers by performing cutting of coil assembly tube and normalization works of inspection nozzle and cover plate & tube cut during foreign material removal process in finish reheater system & includes preheating, PWHT & hardness testing for the duration of 10 days at boiler U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/FINISH RTEHEATER/BOROSCOPIC/U#1/WO/6463 | 10.03.2023 | 10 DAYS | 650,000 | |
15 | Deployment of resources & manpower for carrying out the pending mechanical works in the areas of mills, feeders & ID FANS of unit#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RMD/SMX/PENDING MECH. WORKS/MILL-E TO J/FEEDERS/ID FAN/WO/6474 | 15.03.2023 | 75 DAYS | 1,875,000 | |
16 | Award of work to provide the resources for carrying out the pending left over works in area of above roof hanger & support in sh.links & riser pipes, headers, roof panel, coil assy. And cold value setting of hangers, flash tank vent pipe pending guide and H&S, cold value setting of hangers & liquidating the pending observation of joint inspection with customer, rectification of eco boiler fill pipe valve -wrong orientation &damage/bend in bypass line of BRP suction valves ,eco upper hanger damage tube rectification with NDT & pending installation of buck stay corner connection @ elevation of 27025 mm at all corners & leveller beams at boiler U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/U#1 LEFT OVER PENDING WORKS IN PP AREA -ABOVE ROOF H&S, FLASH TANK VENT PIPE H&S, BUCK STAY CORNER CONNECTION & LEVELLER BEAM, ECO UPPER HANGER DAMAGE/BEND TUBE RECTIFICATION ETC./U-1 BOILER/WO/6551 | 15.04.2023 | 45 DAYS | 890,000 | |
17 | Award of work to provide the resources for carrying out the pending left over works in area of above roof skin casing works includes attending the leak point of furnace ATT , rection of damage /bend in expansion bellow between furance side vertical plane & furnace side extended wall panel,S-01 sampling line modification & rectification of materal mix up issue in vent & drain links and header guide support of R-14 & S-14 headers in all respect at boiler U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/U#1 LEFT OVER PENDING WORKS/SKIN CASING, DAMAGE EXPANSION BELLOW BETWEEN FURN. VERTICAL WALL PANEL & FURN. EXTENDED WALL PANEL, S-01 SAMPLING LINE RE-ROUTING & MATERIAL MIX UP ISSUE (WRONG GRADE MATERIAL) IN DRAIN & VENT LINKS AND HEADER GUIDE SUPPORT OF R-14 &S-41 HEADERS/WO/6564 | 17.04.2023 | 30 DAYS | 1,800,000 | |
18 | LEFT OVER PENDING WORKS/SH.SPRAY PIPING SUPPORT, DISLODGE OF STEAM COOLED SPACER TUBE FROM CONNECTOR ASSY.IN SH.FINISH & SH. PLATEN REAR COIL ASSEMBALY, STARTS UP SYSTEM SUPPORT, LRSB KNEF BRACKET SUPPORTS, INSTALLATION OF FURNACE FLAME VIEWING CAMERA (CCTV) SPIGOT (FLANGE PORTION), REAR ARCH ENCLOSURE ACCESS DOORS & SCAFFOLD DOOR HOLDING/HANDING ARRANGEMENTS ECT./WO | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/U#1 LEFT OVER PENDING WORKS/SH.SPRAY PIPING SUPPORT, DISLODGE OF STEAM COOLED SPACER TUBE FROM CONNECTOR ASSY.IN SH.FINISH & SH. PLATEN REAR COIL ASSEMBALY, STARTS UP SYSTEM SUPPORT, LRSB KNEF BRACKET SUPPORTS, INSTALLATION OF FURNACE FLAME VIEWING CAMERA (CCTV) SPIGOT (FLANGE PORTION), REAR ARCH ENCLOSURE ACCESS DOORS & SCAFFOLD DOOR HOLDING/HANDING ARRANGEMENTS ECT./WO | 17.04.2023 | 45 DAYS | 1,950,000 | |
19 | Award of work (package-C/I) for the deployment of reqired manpower & resources for carrying out the transporttation of fresh tubess supplied from BHEL trichy for lifting lug seepages restoration works in SH . Finish front & rear coil assy and SH. Platen rear coil assy., erection of fresh tubes to the required work area IE: Location EL-93 metel and providing the resources for cutting the fresh supplied tubes to the required spool length & its edge preparation. (total no. of fresh tubes 484 nos.) for the duration of 20 days AT 2X800 MW, NTPC, TeSTPP,RAMAGUNDAM SITE | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/TRANSPORTATION &ERECTION/FRESH TUBES /PACKAGE-C/1/WO/6505 | 18.04.2023 | 20 DAYS | 1,870,000 | |
20 | Deployment of separate agency for providing required resources & manpower,i.e. IBR WELDER & T&Ps and daily erection & shifting of the full argon cylinders to the required work location ie:EL-93 meter and lowering of emplty cylinders to ground level for refilling purpose for carrying out the welding of butt joints of fresh tubes after clearance of butt joint fit up inspection in S-33 SH. platen rear coil assy.(total no. of butt joints-968 NOS.) of U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RMD/SMX/S-13,S-39 & S-40/WELDING/BUTT JOINT/PACKAGE-C/V/WO/ 6512 | 21.04.2023 | 15 DAYS | 1,982,000 | |
21 | Award of work for the deployment of separate agency for providing required manpower & resources ie: IBR WELDERS & T&Ps for carrying out the seal band welding of seal bands S-33, S-39 & S-40 of replaced tubes (484Nos.) after clearance of fit up inspection at U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/SEAL BAND WELDING S-33, S-39 & S-40/ PACKAGE-C-VI/ WO/6511 | 21..04.2023 | 15 DAYS | 1,185,000 | |
22 | Deployment of separate agency for providing required resources & manpower for carrying out the affected/defective at upper cut line above roof seal band (only by grinding ) ensuring that the groove radius of roof seal band portion is uniformly maintained as per drawing, then cutting of the affected tube in S-39 SH. finish front coil assy., gouging of roof seal band (only by grinding ) ensuring that the groove radius of roof seal band portion is uniform maintained as per drawing, then cutting of the affected tube at lower cut line as per procedure and removal of affected tubes, furture fit up of fresh supplied tubes in S-39 SH . finish front coil assy. total no. of tubes208 nos.(total no. of butt joints fit up-4166 nos) for a duration of 15 days at U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RMD/SMX/CUTTING OF AFFECTIVE TUBE IN S-39 SH. FINISH FRONT COIL ASSY./PACKAGE-C/III/WO/6510 | 21.04.2023 | 15 DAYS | 1,990,000 | |
23 | | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RMD/SMX/CUTTING OF AFFECTIVE TUBES IN S-40 SH, FINISH REAR COIL ASSY./PACKAGE-C/IV/WO | 25.04.2023 | 15 DAYS | 1,990,000 | |
24 | Hiring of agency for providing required resources & manpower for carrying out cutting of the affected/defected at upper cut line above roof seal band (only by grinding) without damaging adjacent tube in S-33 Sh. Platen rear coil assembly, gouging of roof seal band (only by grinding) ensuring that the goove rdius of roof seal band portion is unformly maintained as per drawing , then cutting of the affected tube at lower cut line as per procedure and removal of affected tube, futher fit up of fresh supplied tube in s-33 Sh. | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RMD/CUTTING OF AFFECTED/DEFECTIVE TUBES IN S-33 SH, PLATEN REAR COIL ASSY./PACKAGE-C/11/WO | 25.04.2023 | 15 DAYS | 770,000 | |
25 | Deployment of separate agency for completing the blance works of side purlins & monorail of bunker, scrap cutting of side purlins structure, monorail of bunkers & erected structure of tripper floors, left out bolting/welding of erected steucture (APPROX.280 MT) | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/BLANCE STR.WORKS/U#01 BUNKER/WO/6602(A) | 10.05.2023 | 60 Days | 1,925,000 | |
26 | Deployent of separate agency to provide resource & manpower for carrying out the rectification work to clear the blockages of tubes in furnace water wall transition panel RHS tube no.187 from & furnace rear screen tube assembly. tube no. 156 from RHS at unit#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/RDM/SMX/U#1-BLOCKAGE OF TUBE IN FURNACE WATER WALL PANEL RHS & FURNACE REAR SCREEN TUBE ASSY/RESTORATION WORKS/WO/6621 | 22.05.023 | 15 DAYS | 1,150,000 | |
27 | S-33 & R-13 FSH &FRH Coil repair works in unit 2 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT FSH FRH REPAIR/2855/LOA | 29.09.2023 | 60 DAYS | 45,432,376 | Completion Certificate Available |
28 | S-33 & R-13 FSH &FRH Coil repair works in unit 2 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT FSH FRH REPAIR/2855/LOA-SUPL ORDER-1/AMD-01/18744 | 31.10.2023 | | | |
29 | S-33 & R-13 FSH &FRH Coil repair works in unit 2 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT FSH FRH REPAIR/2855/LOA-SUPL ORDER-1/Amendment | 18.01.2024 | | | |
30 | Preparation of cleaning tank, tube cutting, tube cleaning & preservation | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT-U2/FRH TUBE CUTTING/0008/WO/6920 | 11.11.2023 | 15 DAYS | 710,000 | |
31 | Deployment of resources for carrying out the left over pending mechanical works in area of mill's, APH & FAN's and liquidation of customer punch points & attending the defects of recent COD activity in boiler unit#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT-U1/MISC ROTARY WORKS/28/WO/6960 | 02.12.2023 | 30 DAYS | 1,325,000 | |
32 | Deployment of resources for carrying out the restoration of defects & tube leakage observed in recent operation of aux boiler & defects like steam leakages due to valve gland failure, valve pssing, HWL-1& HWL-2, control valve passing ect., socket weld leakages of roots valve, seal weld leakages of thermowell and ash leakages from coal piping area and ash leakages from rear arch skin casing arrangement, cracks and distortion in skin casing expansion joint in recents trial run &cod operation of boiler U#1 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT-U1/REC OPR DEFECTS/27/WO/6975 | 07.12.2023 | 30 DAYS | 1,875,000 | |
33 | Carrying out DPT and PAUT of seal weld fillet joints of super heater platen rear coil assembly, super heater finish front & rear coil assembly in boiler unit-2 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT-U2/PAUT-FSH/0024/WO/6952 | 25.11.2023 | 10 DAYS | 970,000 | |
34 | Deployment of separate agency for the procurement, installation and approach platform readiness with handrails for iso kinetic sampler of unit#1&2 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT-U1&U2/WO/70313 | 13.01.2024 | 30 DAYS | 753,000 | |
35 | Carrying out the piping hanger modification of boiler#2 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT-U2/HANGER MODIFICATION/44/WO/7040 | 17.01.2024 | 30 DAYS | 1,185,000 | |
36 | Carrying out the PAUT and DPT for the tube welded attachment location in FRH coil boiler unit-2 | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT-U2/PAUT-DPT/0035/WO/7067 | 05.02.2024 | 7 DAYS | 2,615,000 | |
37 | Floor Finishing work at 30M,55M & 61M including Torquing/Welding/Bolting of structural members/Bracing, Erection of balance member, restoration/replacement of Damaged Floor Grills ete | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT-U1/FLOOR FINISHING-PKG-IV/0054/WO/7166 | 20.03.2024 | 60 Days | 1,086,520 | |
38 | TELANGANA SG ISLAND PACKAGE - DEPLOYMENT OF ADDITIONAL WELDERS FOR U2 ECO STRENGTHENING WORKS AT THE COST OF M/S BHEL | NTPC LIMITED | NTPC Ramagundam, Telangana | 8200408149-034-1057 | 06.04.2024 | | 32982 | Completed |
39 | DEPLOYMENT OF 01 SUPERVISOR , 05 WELDERS, 05 HELPERS, 04 GRINDERS AND 02 RIGGERS FOR THE PERIOD OF 02 (TWO) MONTHS AT PVUNL, PATRATU | NTPC LIMITED | NTPC Ramagundam, Telangana | 5500044441-199-2025 | 19.04.2024 | | 1570318 | |
40 | REGULARIZING PO FOR DEPLOYMENT OF SUPPORTING MANPOWER FOR U2 STUD FIXING WORKS EXECUTED DURING U2 SHUTDOWN WORKS AT THE COST OF M/S BHEL EXECUTING ISLAND PACKAGE | NTPC LIMITED | NTPC Ramagundam, Telangana | 5500044489-034-1057 | 29.04.2024 | | 237395 | |
41 | DEPLOYMENT OF RESOURCES FOR NITROGEN BLANKETING ARRANGEMENT IN BOILER UNIT#1 AT 2X800 MW NTPC RAMAGUNDAM | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT/U1/NITROGEN/0062/WO/7326 | 07.08.2024 | | 315000 | |
42 | REMOVAL OF SCAFFODLING FROM BOILER UNIT#1 OF 2X800MW NTPC RAMAGUNDAM | BHEL | NTPC Ramagundam, Telangana | BHE/PW/PUR/RGMT-U1/SCAFFOLDING/0064/WO/7328 | 09.08.2024 | | 950000 | |
43 | CW PIPE FABRICATION, ERECTION, ALIGNMENT AND WELDING (DIA 2400 MM X 16 MM THICK) | Maruthi Construction / NTPC Ramagundam | NTPC Ramagundam, Telangana | | | | | Ongoing |
44 | CW PIPE ERECTION, ALIGNMENT AND WELDING (DIA 3600 MM X 20/16 MM THICK) | Matajanki / BHEL For NTPC Talcher | NTPC Talcher, Odisha | | | | | Ongoining |